Skip over navigation
Start Content
Town of Danville, Indiana
The Town of Danville is a great place to live, work and do business.
2024 Mill and Overlay Project
Street Maintenance Alert: Milling & Paving Schedule
Attention, Danville residents! This Thursday and Friday, we will be milling, followed by paving on Friday and Saturday.
The remaining streets include:
E. Marion St.: Washington to Tennessee
N. Cross St.: Main to Columbia
Orchard Ln.: Washington to Dead End
Orchard Ct.: Orchard Ln. to Cul-de-Sac
Woodfield Gr.: Washington to Northampton Row
Abbington Sta.: Woodfield to Cul-de-Sac
Parkridge Dr.: Main St. to Danridge
Colonial Ln.: Meadow to Heritage
Tamarack Dr.: Sherwood to Temple
Important Notes:
Schedule Adjustments: The schedule may change due to weather conditions.
No Parking: No parking will be allowed on affected streets during project working hours (7:00 AM - 9:00 PM).
Travel Delays: Drivers should expect travel delays. Some extended delays may occur, so alternate routes are recommended.
Surface Conditions: Expect a rough surface until the new asphalt is laid, as the milling process may leave the road uneven for several days.
For Questions:
Contact Public Works:
Email: apitcher@danvillein.gov
Phone: 317-745-4180 ext. 4000
Thank you for your cooperation and understanding as we work to improve our community’s roads.