Upcoming Road Closures and Detours: Eastside Interceptor Sewer Improvements

🚧 Upcoming Road Closures and Detours: Eastside Interceptor Sewer Improvements 🚧

The project will be carried out in three phases, each impacting different areas and entrances. Please note that dates are subject to change due to weather and unforeseen challenges.

Phase 1:

  • Affected Area: Circle K entrance at 200 E.
  • Detour: Traffic for Circle K will be redirected to the Danville Commons Dr. entrance.
  • Duration: Estimated 2 weeks.
  • Start Date: July 25, 2024

Phase 1

Phase 2:

  • Affected Area: Entrance to Walmart off of 200 E. at Danville Commons Dr.
  • Detour: To enter Walmart, please use the entrance off E. Main St. at Ridge Ave.
  • Duration: Estimated 2 weeks.
  • Start Date: August 1, 2024

Phase 2

Phase 3:

  • Affected Area: E. Main St. will be closed just east of Ridge Ave. and just west of the roundabout. The entrance to the Hendricks County 4-H Fairgrounds off E. Main St. across from Ridge Ave. will also be closed.
  • Duration: Estimated 3 weeks.
  • Start Date: August 19, 2024